Building structure


First structure built with mortar, and second structure started to construct


Plywood walls assembled and the roof with chimney set


Wood screws and wires set on outside surface in order to reinforce the mortar


Mortar works in the wood deck, and after the complete


Painting violet on wall, cream on door and windows


Painting gray on roof, and set in the forest after complete


New stationmaster


New stationmaster Pascal walking on stone pavement in south garden and on stone path in west garden


He inspects the tracks and oversees the train service.


In the house, Pascal lies back on carpet, and watches the G gauge train.


Sitting on the stationmaster's position in south garden and on the top of the mountain


At brick circle in front of the porch


West garden


AB20+AB10 train in the Westgarden station (changing name to "Rose station") , and the west garden after lawn cutting (before the river construction)


Service report


The side step plates set up to 5cm higher to prevent the touch of a shoe on point machine.


The controller unit of Deki-3 on the seat of coach, and the inside of Kato 7ton (notice the second silencer)


Painting house


Before painting, and the scaffold set up in starting of the construction


White surfacer painted on the north wall and east wall


My wife painted her wood plant pots with paint material given from the painter


Painting skyblue on south wall, and the bench painted by my wife


O scale locos and rolling stock


On3 Shay and Climax on the cabinet in my hobby room


Close-up view of another Climax (On3) and the works car (On30)


Live steam on 45mm gauge


Rubby and Mini running on the endless track in west garden


Stationmaster Pascal looking from the mountain, and Shay running with smoke


Reports from the others


Mr. Hoshino's strange steam locomotive on veranda track in his house and Mr. Kashio's DL in his garden railway Gulliver Line


River works


The river construction started in the west garden, at first, the concrete stream was removed.


Digging the ground in wider and deeper than existent stream


The trench appeared in the center of west garden and under the arch bridge.


Concreting works


Many concrete blocks carried into the site, and the concrete mixer set in south garden


The deep ditch built behind the arch bridge, and small pond constructed under sidetrack


The large crescent pond built on stream line, and the pond constructed under the arch bridge